Calculate risked reserves and Expected Monetary Value (EMV) using probabilistic volumes (P10/P50/P90), geological risk factors, and economic parameters. Includes decision tree analysis, Monte Carlo simulation, and sensitivity tornado charts for prospect evaluation and portfolio optimization.
PERT Distribution:
Mean = (P10 + 4×P50 + P90) / 6
This assumes a lognormal-like distribution where P50 is the median and P10/P90 represent the 10th and 90th percentiles.
Risked Volumes:
Risked Mean = Mean × PoS
Where PoS = Pg × Ps × Pr
Decision Tree Formula:
EMV = (NPV_success × PoS) - (Cost_failure × (1-PoS))
Success Branch:
Failure Branch:
Decision Rule:
If EMV > 0, the prospect has positive expected value and should be considered for drilling.
Randomly samples from the P10-P90 volume distribution using lognormal assumptions to generate thousands of realizations. This produces: